WATCH US BUILD
CLICK ON THE LINKS BELOW TO VIEW THAT PHASE OF CONSTRUCTION.
STAGE ONE---TO THE CONCRETE SLAB
CUTTING TREES----MAY 28, 2000
EXCAVATION----MAY 30, 2000
LAYING OUT THE HOUSE---JUNE 2, 2000
DIGGING THE FOOTINGS--JUNE 5, 2000
FOOTINGS---JUNE 6, 2000
PUMPING CONCRETE----JUNE 7, 2000
SETTING BLOCK----JUNE 7, 2000
BUILDING THE STEM----JUNE 8, 2000
GROUTING THE STEM----JUNE 9, 2000
BACK FILLING THE STEM----JUNE 12, 2000
LAYING OUT THE PLUMBING----JUNE 16, 2000
PLUMBING ROUGH-IN----JUNE 19, 2000
INTERIOR FOOTINGS----JUNE 27, 2000
SLAB PREP-----JUNE 28, 2000
RADIANT HEATING---- JULY 7, 2000
CONCRETE SLAB----JULY 14, 2000
STAGE 2---FLOORS AND WALLS
BRICK FLOOR PREP----JULY 21, 2000
BRICK FLOORS----JULY 26, 2000
STOCKING ADOBE----AUGUST 3, 2000
LAYING ADOBE----AUGUST 8, 2000
ADOBE WALLS----AUGUST 13, 2000
MORE ADOBE WALLS--AUGUST 15, 2000
AND MORE ADOBE WALLS----AUGUST 16, 2000
STILL MORE ADOBE WALLS----AUGUST 16, 2000
EVEN MORE ADOBE WALLS----AUGUST 21, 2000
CUTTING THE LINTELS----AUGUST 23, 2000
SETTING THE LINTELS----AUGUST 23, 2000
BOND BEAM FORM----AUGUST 25, 2000
FIRST FINISHED BOND BEAM----SEPT. 1, 2000
STAGE THREE---BEAMS/PORTALS/DECKING
BEAMS--SEPT. 5, 2000
FRAMING--SEPT. 6, 2000
MORE BEAMS--SEPT. 6, 2000
ADOBE BLOCKING--SEPT. 8, 2000
MORE BOND BEAM--SEPT. 12, 2000
MORE FRAMING--SEPT. 13, 2000
NOOK/DINING ROOM--SEPT 14, 2000
FIREPLACES--SEPT. 15, 2000
MORE FIREPLACES--SEPT. 18, 2000
TALLER WALLS--SEPT. 18, 2000
STILL MORE FIREPLACES--SEPT. 20, 2000
BEAMS AND VIGAS--SEPT. 22, 2000
PORTAL--SEPT 22, 2000
THE LAST BOND BEAM ???--SEPT 26, 2000
DOUBLE BOND BEAMS--SEPT. 27, 2000
GARAGE WALLS--SEPT 28, 2000
BUILDING THE BOVIDA-- OCTOBER 7, 2000
EDDY BLOCKING-- OCTOBER 7, 2000
HAULING TRASH-- OCTOBER 7, 2000
LATILLAS--- OCTOBER 14, 2000
RAIN DELAY--- 0CTOBER 14, 2000
ADOBE-- OCTOBER 14, 2000
GARAGE WALLS 2-- OCTOBER 14, 2000
FINISHED BOVIDA---OCTOBER 14, 2000
NAILING DOWN LATILLAS-- OCTOBER 21, 2000
THE LAST BOND BEAM, AGAIN--OCTOBER 21, 2000
GARAGE INTERIOR WALLS--OCTOBER 21, 2000
GARAGE PARAPET---OCTOBER 21, 2000
GARAGE DECKING--OCT. 28, 2000
MORE GARAGE PARAPET--OCT. 28, 2000
PLUMBING TOP OUT--OCT. 28, 2000
VACATION-----NOVEMBER 11, 2000
DECKING----NOV. 11, 2000
DOUBLE ROOF----NOV 18, 2000
PROGRESS PHOTO---NOV. 18, 2000
MORE DOUBLE ROOF--NOV. 26, 2000
GRINDING THE PARAPET--NOV. 26, 2000
THE INTERVIEW---NOV. 30, 2000
THE PHOTOGAPHER---Nov. 30, 2000
THE BIRTHDAY ----NOV. 30, 200
FINAL ADOBE COUNT---DEC. 10, 2000
SUBCONTRACTORS---DEC. 10, 2000
NOTCHING THE WALLS---DEC. 10, 2000
WIRING--DEC, 17, 2000
INSULATION ---DEC. 17, 2000
ROOF SHEATHING---DEC. 17, 2000
READY FOR THE ROOFERS--DEC. 17, 2000
ADOBE WALL INSULATION--DEC. 17, 2000
WINDOWS--DEC. 24, 2000
SNOW--DEC. 31, 2000
ROOFERS--DEC. 31, 2000
ROOF--DEC. 31, 2000
WINDOW SILLS--DEC 31, 2000
CLICK HERE TO " WATCH US FINISH "